Portfolio Description

CASE STUDY

ROCK FALL CURTAIN WALL

Melbourne, VIC

Cross Yarra Partnership

Construction and Infrastructure

Consulting Services

Rock fall curtain supplied by Geobrugg and installed by Ranger.

CYP needed a solution to stop stray rocks falling into the Franklin East cavern during the pile break out procedure from the Franklin West side. The rock fall curtain was 18m high by about 16m wide and was made up of 5 mesh panels and involved the installation of 43 Hilti chemset anchors, eyenuts, a perimeter wire rope and the splicing together of the panels with several hundred 1 tonne shackles as per the Geobrugg design.

Installation was completed in a very tight time frame ahead of schedule and ahead of budget.